Progress Updates & News

December 16, 2014

Construction completed March 2013.  Work underway to address final deficiency.

March 5, 2013

Completion of phases:  Phase 1 – Completed by September 1, 2012 and students attending classes at facility.  Phase 2 – Main floor and Mezzanine – completed February 2013; Basement (Lab space) to be completed March 2013.

December 14, 2012

Completion of phases:  Phase 1 – Completed by September 1, 2012 and students attending classes at facility.  Phase 2 – to be completed January 2013.  Required demolition for Phase 2 underway.

October 17, 2012

Lease executed.  Completion of phases:  Phase 1 – completed by September 1, 2012 and students attending classes at facility. Phase 2 – to be completed by January 2013. Required demolition for Phase 2 underway.

June 26, 2012

Conditional offer to lease executed. Lease being finalized. Budget exceeds confirmed funding sources. Various cost reduction and additional funding strategies being pursued. Construction scheduled to commence June 25, 2012.  Completion of phases: Phase 1 – September 1, 2012 and Phase 2 – January 2013.

May 8, 2012

 Board 2 Approval

March 6, 2012

 Board 1 Approval

April 17, 2012

 Planning Brief - Planning & Priorities Committee (P&P) Review